Peritas were engaged by Process 26 to integrate the structural elements of a 500,000 tpa gravity gold circuit into an existing Ni-Cu flotation plant.

The scope included maximizing the reuse of existing equipment. In conjunction with Artemis, a process flow diagram and mass balance were developed for the integrated gold circuit. Peritas performed all civil & structural, engineering for the gravity circuit integration.

Onsite activities consisted of the following:

  • Installation of all concrete and civil works
  • Refurbishment of primary and secondary crushing station
  • Integration of a new Metso HP200 tertiary crusher
  • Structural audit & repairs to existing plant in accordance with DMIRSrequirements
  • Replacement of RE Wall with mass retaining wall
  • Refurbishment of existing mills
  • Supply and installation of DSM screen and cyclones for mill classification
  • Supply and installation of gravity circuit feed conveyors
  • Supply and installation of gold room and security system
  • Redesign and refurbishment of HV Electrical distribution network
  • Refurbishment of LV electrical reticulation system
  • Upgrade of SCADA system
  • Relocation and installation of new 10m tails thickener
  • Raw water dam refurbishment
  • Air and water system upgrade

contact us

PERTH OFFICE

+61 8 6336 9299

enquiries@peritasgroup.com.au

74 Goodwood Parade, Burswood WA 6100

MELBOURNE OFFICE

+61 3 8657 9292

enquiries@peritasgroup.com.au

St Kilda Rd Towers, Suite 350, 1 Queens Rd, Melbourne VIC 3004

BRISBANE OFFICE

+ 61 7 3074 0157

enquiries@peritasgroup.com.au

Riparian Plaza, 38/1 Eagle St. Brisbane QLD 4000

have a project you'd like to discuss? get in touch.